- Concrete: To be scheduled
- Hydrant: Not applicable
- Milling: June 23 to June 28, 2026
- Paving: June 29 to July 5, 2026
Underground Pipe and Asphalt Replacement
UPAR
2026 UPAR Projects schedule
Scheduled dates may change due to weather, and other delays. Thank you for your patience during our short construction season.
16th Avenue between 91 and 92nd Street
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 28 to August 2, 2026
- Paving: July 3 to August 9, 2026
16th Avenue between 102 and 105th Street and 1600 Block of 105th Street
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 16 to July 21, 2026
- Paving: July 22 to July 28, 2026
1600 and 1700 Blocks of 93rd Street and 17th Avenue from 92nd to Kinsmen Park
- Concrete: Not applicable
- Hydrant: June 15 to June 24, 2026
- Milling: August 6 to August 11, 2026
- Paving: August 12 to August 18, 2026
17th Avenue between 96 and 99th Street
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: August 6 to August 11, 2026
- Paving: August 12 to August 18, 2026
21st Avenue between 97th Drive and 99th Street and 99th Street between 20th and 21st Avenue
- Concrete: June 10, 2026 to June 26, 2026
- Hydrant: June 8 to June 17, 2026
- Milling: July 16 to July 21, 2026
- Paving: July 22 to July 28, 2026
25th Avenue between 98 and 99 Street
25th Avenue between 98th Street North and 99th Street Service Road / Highway 4 North
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: June 8 to June 13, 2026
- Paving: June 14 to June 20, 2026
103rd Street 1800 and 1900 Blocks
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 6 to July 11, 2026
- Paving: July 12 to July 18, 2026
103rd Street from Railway Avenue and 11th Avenue
- Concrete: June 1 to June 17, 2026
- Hydrant: Not applicable
- Milling: June 18 to June 23, 2026
- Paving: June 24 to June 30, 2026
104th Street from Railway Avenue to 9th Avenue - Deferred
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: Not applicable
- Paving: Not applicable
Deans Crescent and Panton Avenue
Deans Crescent between Panton Avenue and Panton Avenue between Deans Crescent and 95th Drive
- Concrete: August 1 to August 17, 2026
- Hydrant: ✅ Complete
- Milling: August 18 to August 23, 2026
- Paving: August 24 to August 30, 2026
- Concrete: July 13 to July 29, 2026
- Hydrant: ✅ Complete
- Milling: August 4 to August 9, 2026
- Paving: August 10 to August 16, 2026
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 4 to July 9, 2026
- Paving: July 10 to July 16, 2026
- Concrete: July 1 to July 17, 2026
- Hydrant: Not applicable
- Milling: July 18 to July 23, 2026
- Paving: July 24 to July 30, 2026
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 27 to August 1, 2026
- Paving: August 2 to August 8, 2026
- Concrete: Not applicable
- Hydrant: Not applicable
- Milling: July 2 to July 7, 2026
- Paving: July 8 to July 14, 2026
- Concrete: ✅ Complete
- Hydrant: Not applicable
- Milling: July 14 to July 19, 2026
- Paving: July 20 to July 26, 2026
UPAR Information
Each year, the City Council approves several infrastructure improvement projects in North Battleford, funded by a portion of the taxes paid by property owners through the Underground Pipe & Asphalt Replacement (UPAR) levy.
UPAR construction is scheduled to take place from mid-May through the fall of this year. Timelines will be communicated to community members in advance, particularly to those whose neighbourhoods and properties will be directly affected by the necessary work conducted by the City and its contractor.
UPAR
Underground Pipe & Asphalt Replacement
MAC
Maximum Accepted Concentration
Sanitary Sewer
An underground pipe or tunnel system for transporting sewage from houses and commercial buildings (but not stormwater) to a sewage treatment plant for disposal.
Sub-base
The layer of aggregate material that lies immediately below the pavement and usually consists of crushed aggregate or recycled materials
Milling
The process of removing at least part of the surface of a paved area such as a road, bridge, or parking lot
Service Line
The pipe or conduit, water meter, and valves connected on one end to the curb stop, the other end terminating inside the User's building, to provide water service
Potable Water
Water that is considered safe to drink
Service Trench
Used for installation of underground infrastructure or utilities (such as gas mains, water mains, communication lines, and pipelines)
Temporary Service
A 1-1/4" poly service line that will be set up in your back alley (commercial) or in the front of your property (residential) to provide alternate accessibility to City main water lines during construction periods - intended to provide the property owner with access to (non-potable) water during lengthy service disruptions - a boil water advisory accompanies a temporary service to ensure the water is safe for human consumption
For Residents in the UPAR Construction Areas
The City of North Battleford is legally required to replace any lead service lines encountered during the underground UPAR work. Property owners can take advantage of this opportunity to replace their water and sewer lines with updated materials (if not lead) at a reduced cost.
For more information, contact 306-441-0359 (text or call).
The deadline for property owners to request replacement of their underground laterals was May 15, 2025.
To ensure garbage and recycling cart pickups are not missed for the properties within a UPAR construction area, residents are asked to put their collection bins in front of their residence and the UPAR contractors will move the bins to a location where they can be accessed by Loraas.
For any questions, please contact 306-441-0359
Parking and Access During Construction
During the UPAR project, parking restrictions for property owners on blocks currently under construction will not be enforced. Property owners may park on adjacent blocks to access their properties during the construction period.
Motorist and Pedestrian Access
Details to come later.
Additional Information
Public information sessions will be held on Zoom every two weeks for the duration of the project, featuring updates and timelines from the contractors completing the UPAR work.
Information session dates to be posted when dates are established.
Thank you
We understand that this process, while necessary, can be frustrating for our community. We appreciate your cooperation and encourage you to reach out with any questions or concerns.
Project Contact
Department of Engineering, Planning, Asset Management & Infrastructure
1291-101st St
North Battleford, SK
S9A 2Y6
For assistance related to UPAR, please feel free to:
- Call 306-441-0359
- Text message
- or Email