Capital Works Projects 2018
Update August
August 7th 2018

101st Street – 12th to 14th Avenue

Roadway reconstruction work is complete along the 1200 block of 101st Street and the block is opened to vehicles and pedestrians. Tree planting and street fixture installation is planned for the coming weeks, which will result in some short-term localized road closures. The 1300 block is closed to traffic and pedestrians while roadway reconstruction is underway. The 1300 block will remain closed for 6-8 weeks. Access to affected businesses will be disrupted while the work proceeds. Please see the attached business access map showing alternate construction access locations on the 1300 block. The project is expected to be completed by September 14th. No further water service disruptions or drinking water advisories are expected. Roadways work is being performed by K&S Asphalt.

 

Deanscroft Avenue and 112th Street Storm Sewer

Storm Sewer Manhole installation is completed, with roadway restoration planned for the coming weeks. Underground work was performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

Cured in Place Pipe (CIPP) Sewer Lining Program

CIPP lining work is completed, the work was performed by Insituform Technologies.

 

Thomas Avenue and Abbott Avenue rehabilitation

The project is complete and opened to traffic. Underground work was performed by City crews, and Unicon Pipeline, and Roadways by K&S Asphalt.

 

Douglas Avenue and 101st Crescent rehabilitation

Paving work is underway along Douglas Avenue and 101st Crescent from 101st Street to Dunning Crescent. Temporary localized road closures will be in effect as the work proceeds. The project is expected to be completed by August 10th. Underground work was performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

105th Street – 10th to 11th Avenue rehabilitation

Underground Utility work is completed and roadway reconstruction will begin August 7th. The road will remain closed while the work proceeds. A Drinking Water Advisory is in place while the new water pipes are being commissioned. Affected residents will be notified once the advisory has been lifted. Roadway reconstruction is expected to be completed by August 24th. Underground work was performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

98th Street 17th to 18th Avenue rehabilitation

Underground Utility work will begin August 6th along 98th Street from 17th to 18th Avenue. Road closures, water service disruptions, and drinking water advisories will be in place. Roadway restoration will follow the underground work, and is expected to be completed by September 21st. Underground work will be performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

 

15th Avenue Water Main connection – 107th to 110th Street

Underground Utility work is planned for September 4th to September 15th along 15th Avenue from 107th to 110th Street. Road closures, water service disruptions, and drinking water advisories will be in place. Roadway restoration will follow the underground work and is expected to be completed by September 21st. Underground work will be performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

20th Avenue Sanitary Sewer connection – 100th to 101st Street

Underground Utility work is planned for September 15th to September 30th along 20th Avenue from 100th to 101st Street. Road closures, water service disruptions, and drinking water advisories will be in place. Roadway restoration will follow the underground work and is expected to be completed by October 15th. Underground work will be performed by Unicon Pipeline, and Roadways by K&S Asphalt.

 

Civic Centre Parking Lot

Paving work is completed and the area is open to traffic.

 

Killdeer Park

Roadway and shallow buried utilities construction is underway and expected to be completed August 10th for Sandpiper Road and Finch Crescent. The area will remain closed as the work proceeds.

 

More detailed schedule information will be provided as it becomes available. Updates on the progress of the projects are available at www.cityofnb.ca, or by following the City of North Battleford on Facebook or Twitter.

 

The City urges motorists to use caution when travelling through the work zones, and respect the safety of workers. The patience and understanding of the public, residents and businesses in affected areas is appreciated during these important rehabilitation projects.

A business access map for the 1300 block of 101st Street is embedded below or follow the link below.

 

For more information:

 

Jennifer Niesink, Director of Planning and Development
306-445-1718 | jniesink@cityofnb.ca

 

Dustin Tungilik MacDonald, Acting Communication Coordinator
306-445-1713 | dmacdonald@cityofnb.ca

 

 

 