Capital Works Project Update

September 28th 2017

Capital Works Project Updates for September 28th, 2017

 

105th Street – 11th to 12th Avenue, and 12th Avenue - 104th to 105th Street

This project is complete and the road is opened to traffic.

 

101st Street – 11th to 12th Avenue, and 12th Avenue – 100th Street to 102nd Street

A number of small factors have caused the completion of the project to be delayed by 1 week.  The project is expected to be complete October 16th. Concrete curb work and street light installation will be completed this week, with paving stone work continuing for the coming weeks on 12th Avenue. Paving, sign and fixture installation, crosswalk construction, tree planting and line painting are all planned for next week as well. Sections of sidewalk on 101st street have been opened to pedestrian traffic while the work continues, but 101st Street will remain closed to vehicle traffic until the completion date.  12th Avenue between 100th and 102nd streets will remain closed to vehicles and pedestrians while sidewalk and roadway construction is underway. Roadway reconstruction work is being performed by G&C Asphalt.

 

This work will impede access to businesses in the area, however businesses will still be open and operational. Contact the business you plan to visit to identify the best alternative access.

  

97th Street – 13th to 15th Avenue

Underground pipe replacement work is complete, and Drinking Water Advisories have been lifted. Roadway re-construction is underway, with concrete curb and sidewalk repairs planned to begin next week. The project is expected to be completed by October 6th.  Roadway reconstruction work is being performed by G&C Asphalt.

 

99th Street – 12th to 13th Avenue

Underground pipe replacement work is underway with road closures and drinking water advisories in effect. Underground work is expected to proceed for the next two weeks. Roadway re-construction will follow completion of the underground work, and proceed for a further two weeks. The project is expected to be completed by October 20th.  Underground pipe replacement work is being performed by Sanburn Construction, and Roadway work by G&C Asphalt.

 

Killdeer Park Development

Concrete curb and sidewalk work is complete and the construction of roadway granular courses is underway.  Paving and shallow buried utilities work are planned to begin in the coming weeks.  Roadway work is being performed by G&C Asphalt.

 

18th Ave/Diefenbaker Drive/St Laurent Drive - 100th Street to Mckenzie King Crescent - Roadways

This project is complete and the road is opened to traffic.

 

Henderson Drive/Amos Drive Lane - Buhler Ave to Territorial Drive 

Back alley construction is expected to begin in early October.  This work will be performed by G&C Asphalt.

 

Airport CAP Runway 12-30 Resurfacing Project

This project is complete and the Runway is opened to air traffic.

 



View PDF Document