Capital Works Project Updates

June 6th 2017

Below is an update on the Capital Works Construction Projects:

Hydrant Replacement Program

The Hydrant replacement program has been completed with sidewalk and roadway patching planned for the following weeks.


17th Avenue – 105th to 107th Street


Underground pipe replacement work will continue for the remainder of the week.  Drinking water advisories and road closures will be in effect in the area.  Roadway reconstruction is scheduled to begin once the underground work is complete.


105th Street – 11th to 12th Avenue, and 12th Avenue - 104th to 105th Street


Underground pipe replacement work is scheduled to begin June 6 along 12th Avenue between 104th and 105th Street.  Work is then expected to move to the 1100 block of 105th Street beginning the week of June 19, proceeding for approximately 4 weeks.  Drinking water advisories and road closures will be in effect in the area.  Roadway reconstruction is scheduled for the following weeks.


101st Street – 11th to 12th Avenue, and 12th Avenue – 100th Street to 101st Street


Underground pipe replacement work is scheduled to begin June 12 along 101st street and commence for approximately 3 weeks.  Underground pipe replacement work is scheduled to begin July 10th along 12th Avenue, proceeding for approximately 2 weeks.  Street reconstruction will begin once the underground work has been completed and will proceed for a further approximately 4 weeks.  Drinking water advisories and road closures will be in effect in the area. Although access to businesses from 101st Street will be closed for the duration of the project the businesses will remain open. Please contact the individual businesses for information on access.


97th Street – 13th to 15th Avenue


Underground pipe replacement work is scheduled to begin July 3, lasting for approximately 6 weeks.  Road closures and Drinking Water Advisories will be in effect. Roadway re-construction will follow completion of the underground work and will proceed for a further 3 weeks.


99th Street – 12th to 13th Avenue


Underground pipe replacement work is scheduled to begin August 14, lasting for approximately 3 weeks.  Road closures and Drinking Water Advisories will be in effect. Roadway re-construction will follow completion of the underground work.


Killdeer Park Development


Underground pipe work is nearing completion with roadways work scheduled to begin June

12.


Civic Centre Parking Lot


Reconstruction of the North Parking Lot behind the Civic Centre is scheduled to begin June 6, and will take approximately 2 weeks.


More detailed schedule information will be provided to property owners as it becomes available.  Updates on the progress of the projects are available at www.cityofnb.ca, or by following the City of North Battleford on Facebook or Twitter.